The project consisted of a new manufacturing and corporate facility for Ecopax, a styrofoam products manufacturing company. Alliance provided design and documentation services for the pre-cast concrete shell building and the interior fit-out. Included in the fit-out were corporate, production, & shipping offices, a large multi-purpose break room, locker rooms, and a trucker's lounge. The east end of the building was constructed of metal panels to allow for future expansion.
| Location: | Lehigh Valley Industrial Park VII 1355 Easton Road Bethlehem, PA 18015 |
||||||||||||||
| Program:  |
|
||||||||||||||
| Total Area:  | 144,000 SF | ||||||||||||||
| Status:  | Completed - November 2017 |
| Project Team | |
|---|---|
| Owner:  | Ecopax, LLC |
| Construction Manager:  | JVI LLC |